The real question
What evidence demonstrates a correctly installed hanger?
Acceptance does not rely on one indication; component identity, procedure, operating values, test results and responsible sign-off must form a consistent chain.
Technical model
Before installation
Check part/serial identity, drawing revision, seal material, running tool, bowl condition and cleanliness.
During installation
Record depth/position, weight response, torque/turns or other approved indicators; verbal memory is not sufficient.
After installation
Test required boundaries independently, retain charts/records and document final valve/plug/port status.
Controlled sequence
From identification to evidence
- 01Identity↓
- 02Clean/inspect↓
- 03Land/lock↓
- 04Test/record
Field application
What does this change in the field?
A good report tells the next team what was installed, by which method, in what condition and with what result.
Glossary
Key terms
- Traceability
- Ability to link component, records, operation and test.
Learning check
Reason through the operating case
If a pressure chart exists but the hanger serial number is missing, what remains unresolved?
Answer and reasoning
Traceability is incomplete; the test cannot be reliably tied to the installed component and its material/manufacturing records.
Technical sources
The sequence is based on Eng. Kamal Deilami’s wellhead equipment reference and cross-checked against official manufacturer and technical sources. It does not replace manufacturer instructions or the approved well programme.