YAS Academy · Wellhead pathway

Chapter 5 · Lesson 27 · W04

Reading and verifying a complete wellhead arrangement

Integrating load, pressure, flow and records

The final lesson reads the assembly through four concurrent maps: load path, pressure barriers, flow/annulus paths and document trail; no generic image replaces the well-specific GA, P&ID and programme.

Teaching schematic of system pathsNot to scale or manufacturer-specific; operations require the approved well-specific GA, P&ID and procedure.

The real question

How can an unfamiliar stack be analysed quickly without guessing?

Start with identity and orientation; move bottom-up through components; trace every casing/tubing/annulus; then valve line-up and pressure envelope; finally capture discrepancies and hold points.

01Mechanical load
02Pressure boundary
03Production path
04Annulus / control

Technical model

01

1) Identity and orientation

Match well ID, equipment tag, manufacturer/model, serial, orientation and upstream/downstream direction to records.

02

2) Engineering paths

Trace load path, pressure boundary, production bore and annuli separately on the GA or markup.

03

3) Operating state

Record valve positions, gauge range, trapped pressure, caps/plugs, control power and downstream readiness.

04

4) Evidence and handover

MTCs, pressure charts, torque/tension records, NCRs, as-builts and sign-off must link to the physical equipment.

Controlled sequence

From identification to evidence

  1. 01Identify
  2. 02Trace
  3. 03Verify
  4. 04Test
  5. 05Record/handover

Field application

What does this change in the field?

An unidentified component, unknown seal status, fastener/rating mismatch or invalid test record is a deviation—not an invitation to guess.

Glossary

Key terms

Walkdown
Structured field inspection against documentation.
As-built
Record revised to match the actual installed condition.

Learning check

Reason through the operating case

Design a short walkdown before handover to operations.

Answer and reasoning

Identity/records; condition and orientation; four-path tracing; line-up and known/zero pressures; test/torque records; tags/signage; deviations; bilateral handover sign-off.

Technical sources

The sequence is based on Eng. Kamal Deilami’s wellhead equipment reference and cross-checked against official manufacturer and technical sources. It does not replace manufacturer instructions or the approved well programme.