The real question
What is the minimum information needed to approve an interface?
Each side has an independent data record; approval follows only after all critical fields match and discrepancies are resolved by engineering documentation.
Technical model
Identity and geometry
Verify manufacturer, model, part/serial, revision, nominal size, bore, face/groove and envelope.
Pressure and service
Assembly rating follows the weakest approved boundary; temperature, fluid compatibility and sour-service requirements also require review.
Installation and proof
Tooling, lifting, fasteners, seal lot, torque/tension and test procedure are closed before execution.
Controlled sequence
From identification to evidence
- 01Collect↓
- 02Compare↓
- 03Resolve↓
- 04Approve↓
- 05As-built
Field application
What does this change in the field?
‘It fitted a similar well before’ is not a substitute for drawings and approval.
Glossary
Key terms
- Hold point
- A stage requiring documented approval before work continues.
Learning check
Reason through the operating case
If the upper component has a smaller bore but adequate pressure rating, what follows?
Answer and reasoning
Engineer the restriction's impact on drift, intervention, erosion and flow; pressure rating alone does not establish acceptance.
Technical sources
The sequence is based on Eng. Kamal Deilami’s wellhead equipment reference and cross-checked against official manufacturer and technical sources. It does not replace manufacturer instructions or the approved well programme.